With the aim to provide electricity to all, the Indian government is focusing on
building new power plants in India. It is expected that in the XII Plan period
alone, Indian electricity generation capacity would be enhanced by at least
75,000 mw. All these new power plants needs to be designed for to provide best
efficiencies and utilizing newer technologies such as the use of supercritical steam
generator or advanced class gas turbines. While power plant engineers will design
optimum solutions, the plant once built has to be tested for the "Guaranteed
performance".
Performance testing is not a new trend but a necessity. CEA of India has brought
out its report on existing power plants, which suggest that many existing power
plants require to be renovated and modernized (R& M) and before R&M, the
performance test needs to be done.
Globally, this concept is already popular. At Tractebel Engineering, we have
given our consultancy services in this area in various projects worldwide - seven
nuclear power plants( >5,000 mw), over 50 hydropower plants (>20,000 mw),
over 20 coal-fired power plants ( >28,000 mw), 30-plus combined cycle power
plants (>20,000 mw), 30 cogeneration plants (> 1,000 mw), 30 wind farms
(>500 mw) and other renewables like solar ( both PV and CSP), biomass plants
(> 1,000 mw), etc.
Two of our projects have been recently commissioned. They are the 685-mw CCPP
Al-Dur project in Bahrain and the 2,750-mw CCPP Marrafiq project in South
Arabia. Hence we bring on table the international experience. During our long
journey of providing consultancy services, we have learnt that Performance tests are
an integral part of a quality engineering service program.
DESIGN STAGEDuring the preparation of specifications,
performance guarantee parameters are always
specified. If not, it is always agreed during the
contract signing stage. The ASME PTCs are often
referenced in equipment purchase and/or
engineering, procurement, and construction (EPC)
contracts to provide a standard means of determining
compliance with performance guarantees.
Specifications also include instructions for designing
and executing performance tests at both the overall
plant level and the component level. After the design
of the plant is fixed, a plan for conducting the test and
analyzing its results is prepared and documented. A
well-written plan envisages provisions for both
expected and unexpected test conditions.
Test procedure is established between all
stakeholders before the commencement of the test.
This covers all aspects of health, safety, environment
and performance.
APPLICATION OF CORRECTION CURVES
All performance parameters are guaranteed at reference
conditions. Since the reference conditions are rarely met during
the test conditions, correction curves (for atmospheric pressure,
humidity, CW temp, etc) are normally agreed in the contract.
For example, a plant may be guaranteed to have a capacity of
220 mw at a heat rate of 1,700 Kcal/kWh-under typical reference
conditions with an ambient temperature of 30ºC and relative
humidity of 60 per cent. The purpose of testing is to confirm
whether the plant performs as guaranteed under those specific
conditions. But how do you verify that a plant has met its
guarantees when the test must be done on a dry winter day, with a
temperature of 15ºC and 30 per cent relative humidity? The most
challenging part of the performance testing is correction of
results for differences in atmospheric conditions. Good
Engineering consultants ensure that OEMs and contractors
provide ambient correction factors as a set of correction curves or
formulas for their individual components. Also, as engineering
consultants, we have to integrate the component information into
the overall performance correction curves for the facility.
KNOWLEDGE OF SPECIFIC APPLICATION
The reference conditions for performance guarantees are unique
to every site. For a gas turbine, the condition of the inlet air has
the biggest impact on gas turbine based plants because the mass
flow of air through the turbines (and consequently the power they
can produce) is a function of pressure, temperature, and humidity.
Performance guarantees for steam plants depends more on the
cooling water temperature. The effect of humidity, however, is
more pronounced on cooling towers. A very humid ambient air
reduces the rate at which evaporation takes place in the tower,
lowering its cooling capacity. Downstream effects are an increase
in steam turbine backpressure and a reduction in the turbine generator's
gross capacity
Hence the most important correction for gas turbine plant
performance tests involves compressor inlet air temperature.
Although a site's barometric pressure typically varies by no more
than 10% over a year, its temperatures may range from sub Zero
to almost 50ºC over the period. Because air temperature has a
direct effect on air density, temperature variation changes a unit's
available power output. For a typical heavy-duty frame gas
turbine, a 3ºC change in temperature can affect its capacity by 1
per cent. A temperature swing of 30ºC could raise or lower power
output by as much as 10 per cent.
Beyond site ambient conditions, the PTCs defines the numerous
other correction factors that the test designer must consider and
it is important to include the specific requirements in the testing
procedure to be agreed between the contractor and the
owner/owner's engineer.
PREPARATION OF THE TEST
Before the test begins, an important aspect is the preparation of
the test. Necessary isolation of some systems is made to satisfy
guarantee conditions. Some modifications (temporary
arrangements) are necessary to allow measurements which are
not installed in the system like the flow meters. The measurement
of generator output at the designated points and the requirements
of additional metering may arise for specific schematics.
Instrumentation used to record test measurements should be
selected carefully to have an accuracy class as specified in the test
procedure with calibration certificates. The data acquisition
system along with measuring devices needs to be calibrated to
PTC-46. Wiring up of the measuring instruments to a data
acquisition system connected to laptops for performing real time
calculations is done.
PERFORMING THE TEST
First step is to make a visual inspection of the existing
installation. The schematics which is approved for the test, is the
reference document. If site installations are not matching with the
reference documents then deviations should be discussed and
documented to make sure their impact is understood by all
parties. It is verified that all systems are operating properly. This
is done through planned preliminary tests and such tests shall be
done in steady state conditions with constant load.
The actual test is started at a predetermined time. All the
steady state values are recorded as per the plan in DCS/DAS.
If all the preliminary checks are done properly, the actual
performance tests are actually done with more easiness. This is an
area that requires expertise and good consultants such as
Tractebel Engineering performs a major role. Having done all the
"real" work beforehand, a consulting firm ensures that nothing
changes during the test that may affect the stability of the data.
During the analysis phase, the calculations for the
performance test are done as per the test codes. Necessary
corrections are applied using the contractual correction curves
and the final results compared with the guaranteed
parameters. If the obtained results are found to be within
contractually agreed limits, the performance test is declared
successfully accomplished.
THE FUTURE
In an era of increased participation by private players in power
sector, it is evident that performance testing is given prime
importance. Demonstrating the performance of the power plant
can be critical to its financial success of the plant and also an
endeavor for greener future, performance testing is a way out to
attain maximum efficiency and least operation costs. There will
always be a need to standardize and avoid contractual litigations.
This requires an active participation of all stakeholders—
developers, contractors and consultants.
(Bhupendra Jain is Addl. General Manager - Projects,
Tractebel Engineering Pvt Ltd)