Citec has won a substantial order
from Jacobsen Elektro, one of
the oldest electro-technical
companies in Norway. Jacobsen
Elektro builds, owns, operates and
transfers power stations and
substations. The company both
finances and supplies turnkey
transmission, distribution, generating,
metering and revenue collection
systems to the global power industry.
This joint project is a gas turbine
plant in single cycle configuration,
4xLM6000 GE gas turbine, and the
plant electrical output is 150 mw. The
end customer is Tanesco, Tanzania
Electric Supply Company.
The plant will be located in
Dar es Salaam, Tanzania.
Citec's project scope
includes conceptual, basic
and detailed design for all
needed disciplines,
including consulting
services on the site. The
design phase will last for about eight
months, and the total project duration
is about 12-14 months. On average, the
project will include approximately 25-
30 experts from Citec during the
design phase.