Home News Technical Articles Interviews Cover Story Orders & Contracts
   
Equipment
Power Generation
International
Green Energy
 
NEWS  SPECIAL REPORT

Hydro majors may fire Bihar's thermal plans

Venugopal Pillai ,  Saturday, November 17, 2012, 12:08 Hrs  [IST]

Bihar thermalHydropower majors SJVNL (formerly Satluj Jal Vidyut Nigam Ltd) and Central utility NHPC have shown interest in developing large thermal power projects in Bihar, a senior official of Bihar State Electricity Board told Electrical Monitor by phone from capital city Patna. While this represents a diversification for the hydropower giants, for Bihar it could mean resuscitation of large coal-fired power plants that have been unable to attract private sector developers for years on end.

The BSEB official, who requested anonymity, explained that Bihar had sought to develop three projects-Buxar, Lakhisarai, Pirpainti (each of 2x660-mw)-using Case-2 of the tariff-based competitive guidelines. On its part, the state government would help with land acquisition, environmental clearances, etc. The developer would be selected using tariff-based competitive bidding method. The official explained that coal linkage was to be the responsibility of the developer.

The projects did not meet with encouraging response. Only one of the three projects attracted bids; they were from Vedanta Group and Lanco Group. The bid by Vedanta was found to be deficient. Subsequently, Bihar Electricity Regulatory Commission did not allow processing of Lanco's bid as the competition was reduced to "single bidder" status.

Given that the Case-II exercise has not seen progress the involvement of SJVNL and NHPC could be a welcome development. SJVNL has shown interest in the Buxar project while NHPC would be interested in the Lakhisarai project. SJVNL-a joint venture between the Central government and Himachal Pradesh government-owns and manages the 1,500- mw Nathpa-Jhakhri project that is India's largest operational hydropower project till date. NHPC, a Central PSU, is India's largest hydropower company. The BSEB official said that the two projects will be developed on "cost-plus" basis and not on the tariff-based mode.

The BSEB official also mentioned that efforts are underway to renovate BSEB's only two power generation plants- Muzaffarpur and Barauni. Besides the R&M works, Muzaffarpur will be expanded by adding two units of 195-mw each, while Barauni will see capacity expanded by 2x250-mw. Both these power plants are antiquated and are currently operating at de-rated capacities. The expansion projects should be ready by the end of the ongoing XII Plan period, the official noted.

Meanwhile, Bihar has made some progress in tying up longterm power supply with public and private power producers. The BSEB official explained that 750 mw has been contracted with Essar Power through two agreements, while GMR Group will supply 260 mw on long-term basis. These 25-year agreements will come into effect from 2014. Essar will supply power from its Tori project in neighbouring Jharkhand while GMR will feed power from its Kamalanga project in Orissa. BSEB has also entered into a long-term power purchase agreement with Central utility NTPC.

Biggest hope: Amidst all its attempts at augmenting power availability, the Nabinagar power project is seen as Bihar's biggest hope. Being developed through an equal joint venture between NTPC and BSEB, the Nabinagar (Stage I) involves setting up of three supercritical units of 660- mw each. The foundation stone for this Rs.13,000- crore project was laid in January this year. The project is shaping up on a 3,000-acre expanse at Nabinagar in Aurangabad district. Land acquisition has taken place and NTPC is close to finalizing equipment suppliers. The BSEB spokesperson said that in the second phase of the project, three more units of 660-mw will be added, as against two envisaged earlier.

The bifurcation of Jharkhand in November 2000 left divided Bihar with very little power generation capacity. Even much of its coal exists in districts that are now under Jharkhand. With very little power generation from its own plants, BSEB relies heavily on allocation by Central power generation plants. It spends huge amounts on power procurement and yet cannot fulfill the demands of the state. Revenue collection from power distribution is pathetic, which has atrophied an already fragile power supply chain. Notably, Bihar had to recently contend with failure in privatizing power distribution in the Patna circle, bringing to naught an effort launched in 2009.

The per-capita power availability in Bihar is amongst the lowest in the country. In FY12, Bihar had power availability of 11,250 million kwh that represented a shortfall of 21.3 per cent. This made a poor comparison with the national metric of 8.5 per cent. On the other hand, Jharkhand's power deficit was only 4 per cent.

Bihar has definitely made a beginning but it has a long way to go before it makes historical power shortages history.
 
                 
Post Your RemarkYOUR REMARK
*Name:
* Email :
  Website :

Remark

 
           

© 2017 Electrical Monitor. All Rights Reserved.