Home News Technical Articles Interviews Cover Story Orders & Contracts
   
Equipment
Power Generation
International
Green Energy
 
NEWS  NEWS

NTPC commissions its first supercritical power unit

EM NEWS BUREAU ,  Monday, July 18, 2011, 11:28 Hrs  [IST]

NTPC has commissioned its first supercritical power generating unit, a company release noted. The Central power utility announced the commissioning of one unit of 660-mw at its Sipat power plant in Chhattisgarh. With this, NTPC's total installed capacity including those through joint ventures-now stands at 34,854 mw.

The coal-fired Sipat project in Bilaspur district has three supercritical units of 660-mw (out of which one is commissioned) and two of 500-mw, both of which are operational. The total operational capacity of Sipat, now at 1,660 mw, is slated to go up to 2,980 mw. The project will power the western region including Chhattisgarh, Gujarat, Madhya Pradesh, Maharashtra, Goa and the Union territories of Daman & Diu, and Dadra & Nagar Haveli.

The Sipat power project was commissioned with main plant equipment sourced from Russian and Korean suppliers. While OJSC Power Machines of Russia supplied the turbines, the boiler package was sourced from Korea-based Doosan Heavy Industries. A senior NTPC official said that the remaining two units of the 3x660-mw Sipat (Stage I) project will be commissioned by the end of this fiscal year.

Supercritical plants by NTPC*
Project
Location
Capacity
Main plant equipment supplier
Boiler
Turbine-Generator
Sipat-I Chhattisgarh 3x660-mw Doosan Heavy Industries, Korea OJSC Power Machines, Russia
Barh-I Bihar 3x660-mw JSC Technopromexport, Russia OJSC Power Machines, Russia
Barh-II Bihar 2x660-mw Bharat Heavy Electricals Bharat Heavy Electricals
*Under construction, as of June 30, 2011

It was widely believed that NTPC's Sipat-Stage I, with orders for main plant equipment placed way back in 2004, would be India's first supercritical power project to turn operational. However, the project was fraught with unexpected delays resulting from poor performance of the equipment suppliers. It may be mentioned that Adani Group's Mundra power project in Gujarat is India's first supercritical power project to turn operational. The first unit of the 2x660-mw Mundra (Stage II) project was synchronized in December 2010 while the second reached the same milestone in early June this year. Sepco-III of China has been contracted to supply the main plant package. (See Box Second for Adani)

The NTPC official also mentioned that the power utility expects to commission the Barh (Stage I) supercritical power project in Bihar, in the medium term, without specifying any time frame. This 3x660-mw coalfired plant is also coming up with Russian equipment. OJSC Power Machines is the turbine supplier while boilers are being supplied by JSC Technopromexport. The equipment contract for Barh-I, valued at Rs.jpg3,258 crore, was signed in March 2005. Like the Sipat-I project, the Barh-I project also allegedly faced inordinate delays at the hands of the Russian suppliers.

Second for Adani

Adani Power has the distinction of commissioning India's first supercritical power unit. In December 2010, it synchronized to grid the first unit of its 3x660-mw Mundra (Stage II) power project in Gujarat. It did so in a record time of 36 months. The second unit of the same project was commissioned in June this year. With this, Adani Power has fully commissioned the first two phases of the Mundra project aggregating 2,640 mw, with six units of 330-mw in the first phase and two supercritical units of 660-mw in the second. The supercritical units were supplied by SEPCO-III of China. The same supplier has been contracted to build the third phase comprising three units of 660- mw each, scheduled to commission by March 2012.

Adani Power has targeted to have nearly 6,000 mw of operational power capacity of nearly 6,000 mw by March 2012. Out of this, 4,620 mw will come from the Mundra project and 1,320 mw from the Tiroda supercritical plant in Maharashtra.


NTPC is also in the midst of commissioning Barh-Stage II that is based on supercritical parameters as well. The 2x660-mw project will have its boiler and turbine-generator packages supplied by Bharat Heavy Electricals Ltd (see table.)

India expects that over 60 per cent of the new thermal power capacity targeted for the XII Plan period would come from fuel-efficient supercritical units, while 100 per cent of such capacity in the XIII Plan would be based on this technology.

Untitled Document
DPIL's new EHV cable plant

Diamond Power Infrastructure Ltd has announced the commissioning of a new plant to manufacture EHV cables up to 500kV. The plant was supplied by Mallifer of France, a release by DPIL said. DPIL joins the league of only seven manufacturers worldwide that are capable of manufacturing 500kV EHV cables, the release noted. An official of DPIL told Electrical Monitor that the plant has been set up at Savli in Vadodara, Gujarat.

 
                 
Post Your RemarkYOUR REMARK
*Name:
* Email :
  Website :

Remark

 
           

© 2017 Electrical Monitor. All Rights Reserved.