Home News Technical Articles Interviews Cover Story Orders & Contracts
   
Equipment
Power Generation
International
Green Energy
 
NEWS  POWER

Myntdu Leksha HEP: Formal inauguration soon

EM NEWS BUREAU ,  Thursday, March 29, 2012, 12:04 Hrs  [IST]

Leksha HEPThe 132-mw Myntdu Leksha hydropower project in Meghalaya is set to be formally inaugurated soon, according to Shillong, H. Massar, Superintending Engineer, Meghalaya Energy Corporation Ltd, speaking to Electrical Monitor over phone from Shillong.

Located in Jantia Hills district, the project has three units of 42 mw each. The first unit started commercial operations in November last year, Massar said. While the second unit is scheduled to turn operational by March 15, 2012, the third unit is likely to be commissioned by June. Civil and electromechanical works on all the units have been completed, the MECL official said.

On full commissioning, the Myntdu Leksha project will be the biggest hydropower scheme in Meghalaya and is expected to bridge the demand-supply gap to some extent. Massar said that once all the three units are commissioned, the total hydropower capacity of MECL-owned plants will be around 311 mw. However, this would still be short of the rising energy demands of the growing north-eastern state. Meghalaya also gets from power from Central PSU North Eastern Electricity Corporation Ltd. The peak power demand in Meghalaya is estimated to be around 600 mw.

The commissioning of the Myntdu Leksha project represents an achievement for Meghalaya. In the planning state since the mid-1970s, the project has a history of time and cost overruns. Discussing some of the project impediments, Massar explained that non-availability of funds was the main reason for delays. Flash floods often jeopardized project work resulting in significant cost escalations. Abnormal flooding was experienced in October 2009 and more recently in May 2011. Shortage of skilled manpower and topography-related issues were other challenges that the project had to contend with. Due to geological conditions, there was a significant delay during the excavation of the dam, apart from a steep increase in the volume of concreting.

Leksha HEPWhen conceived, Myntdu Leksha was supposed to have two units of 42 mw each. Project work could start only in October 2004. The third unit was envisaged in January 2008. The total completion cost of the project is estimated to be over Rs.1,000 crore, significantly higher than what was anticipated at the time of technoeconomic clearance.

Meghalaya Energy Corporation Ltd, the generation arm of the erstwhile Meghalaya State Electricity Board, currently has six hydropower plants, excluding Myntdu Leksha, aggregating around 186 mw. These are Umiam (Stage 1 to Stage 4), Umtru and Sonapani.

According to statistics released by Central Electricity Authority, Meghalaya faced a peak power shortfall of 16.3 per cent in the April- January period of 2011-12. Peak demand, estimated at 319 mw, was met to the extent of only 267 mw. Energy shortages were more acute at 24 per cent. In the given period, Meghalaya had an estimated energy requirement of 1,609 million kwh against which 1,225 million kwh could be supplied. Meghalaya is the highest consumer of electricity in northeastern India after Assam.
 
                 
Post Your RemarkYOUR REMARK
*Name:
* Email :
  Website :

Remark

 
           

© 2017 Electrical Monitor. All Rights Reserved.